there's a minor problem with VBP that we find quite annoying.

In order for a child step to be performed, both the step and its parent step need to be checked, right?


This is as expected. However problems arise in the GUI when you start having like 15-20 child steps, and want to mark only ONE of them to be performed. So you check the parent step, and ALL the child steps become checked. So you uncheck the parent step, and ALL the child steps become unchecked. Quite annoying.


Is there a way to check only the parent step, and a child step? Or is there a way to prevent child steps from being checked when you check a parent?

kinook
01-23-2007, 10:06 AM
Hold down the Shift key while clicking.

http://www.visualbuild.com/Manual/projectstepstab.htm

magwo
01-23-2007, 10:12 AM
Thank you. I believe we tried this, but may have tried with Ctrl.