#1
|
|||
|
|||
Bug? - Outlook Task Synchronization
I'm testing out this feature + Outlook task synchronization in 3.5d.
The Help file says the "Flag" attribute from UR is synchronized with the "Status" attribute in Outlook. However, if I flag an attribute in UR as "Completed", the status in Outlook doesn't go to "Completed". This means it isn't possible to flag a task in UR as complete. I have to do it in Outlook. Anything I'm missing? |
#2
|
|||
|
|||
The custom UR "Complete" attribute btw does seem to synchronize to the correct field in Outlook. However, this custom field in UR isn't linked to any other field, so pretty much useless if I want to track the date at which I complete tasks.
|
#3
|
|||
|
|||
Note: I'm using a dutch version of Outlook.
|
#4
|
|||
|
|||
There was a bug that prevented changes to the Flag attribute in UR from updating the status in Outlook when syncing. This is fixed in the latest download (UltraRecall.exe 3.5.4.6 in Help | About | Install Info after installing). Thanks.
|
#5
|
|||
|
|||
Thanks!
|
Thread Tools | |
Display Modes | Rate This Thread |
|
|