Kinook Software Forum

Go Back   Kinook Software Forum > Ultra Recall > [UR] General Discussion
FAQ Community Calendar Today's Posts Search

Reply
 
Thread Tools Rate Thread Display Modes
  #1  
Old 08-14-2008, 03:04 PM
MrAnalogy MrAnalogy is online now
Registered User
 
Join Date: 02-18-2007
Location: Blacksburg, VA
Posts: 56
How to hide "finished" tasks?

One of my uses for UR is as a task manager.

Once I finish a task I'd like to be able to hide it, but I'd like to still know which Project it was assigned to.

For example, I might want to go back and look at what I did (if it was solving a problem or perhaps Beta Testing software,etc.)

Any suggestions?
Reply With Quote
  #2  
Old 08-14-2008, 03:28 PM
ashwken ashwken is offline
Registered User
 
Join Date: 10-16-2005
Location: Blairsville, GA USA
Posts: 431
Looks like this is on the Road Map:
http://www.kinook.com/Forum/showthre...&threadid=3204

- Ability to hide completed items in tree

In the meantime, what if you created a subfolder "Completed" below a given Project, and moved the completed Item to it.
Reply With Quote
  #3  
Old 08-14-2008, 04:03 PM
MrAnalogy MrAnalogy is online now
Registered User
 
Join Date: 02-18-2007
Location: Blacksburg, VA
Posts: 56
Another way...

Thanks.

I found another way. You can use the FLAG attribute to change the color of the item. Flag=Completed, etc.

It would be VERY cool if you could change the FONT to Strike Thru.
Reply With Quote
Reply


Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is Off
HTML code is Off



All times are GMT -5. The time now is 11:47 AM.


Copyright © 1999-2023 Kinook Software, Inc.